DESCRIPTION AND BENEFITS:

The project includes pedestrian improvements at seven intersections along Cleveland Avenue: Camden Avenue, E. 19th Avenue, Kenmore Road, Republic Avenue, Lakeview Avenue, Agler Road, and Lehner Road. Improvements consist of the installation of enhanced crosswalk markings, the installation of Rectangular Rapid Flashing Beacons (RRFB’s) or Pedestrian Hybrid Beacons (PHB’s) at each intersection and installation of new ADA-compliant curb ramps. Minimal pavement resurfacing is required where enhanced crosswalks are being installed and signage/striping will be updated to accommodate these improvements.

Public Involvement:

Project notification documents were distributed by the City and their consultant team consisting of an informational flyer posted at public locations, a notification letter mailed to property owners and residents within the project area, and a comment form for issuing comments. Those documents may be downloaded at the links below. Comments were accepted until October 29, 2021.

Cleveland Avenue Comment Form
Cleveland Avenue Public Notification
Cleveland Avenue Letter

The City received a total of 7 responses during the public comment period which included 22 unique comments and questions. These were consolidated into 13 questions and comments. A response document was sent to everyone who submitted a comment and is also available for download below:

Cleveland Avenue Comment Response Letter

Public Meeting Information:

Cleveland Avenue Open House Flyer
Cleveland Avenue Open House Flyer(Spanish)
Cleveland Avenue Open House Flyer (Somali)

Cleveland Avenue Open House Postcard
Cleveland Avenue Open House Postcard(Spanish)
Cleveland Avenue Open House Postcard(Somali)

Cleveland Avenue Open House Pamphlet 
Cleveland Avenue Open House Pamphle(Spanish)
Cleveland Avenue Open House Pamphlet(Somali)

A public meeting was held at the St. Stephen’s Community House at 1500 E 17th Avenue on May 24th at 11:30am-1pm and 6pm-7:30pm. A presentation was given at each meeting as well as an open house portion that allowed for attendees to view informational exhibits and ask questions of the project team. Those open house meeting materials are available for download:

Informational Card (printable
)
Crossing Type and Location Exhibit
Project Schedule Exhibit
Pedestrian Hybrid Beacon Guide

A virtual presentation was also prepared for those that could not attend the meetings in-person. CLICK HERE for video.

ESTIMATED SCHEDULE:

PHASESTART   FINISH
Design Fall 2020   Fall 2022
Right-of-Way Late 2021   Late 2022
Utility Relocations Fall 2022   Spring 2023
Construction Summer 2023*   Early 2024*

 

*Subject to funding approval by City Council and weather conditions


ESTIMATED COSTS:

PHASECOST
Design $500,000
Right-of-Way $50,000
Utility Relocations $0
Construction $1,300,000



CONTACT INFORMATION:

City of Columbus Design Project Manager Steve Schmidt, P.E., (614) 645-3966
Designer Carpenter Marty Transportation Inc.
Construction contractor To be determined