DESCRIPTION
AND BENEFITS:
This project will widen Central College Road
in both directions at Harlem Road in order to add eastbound and westbound
left-turn lanes. New traffic signals will be mounted at the intersection. The
project will also install new storm sewer lines and extend City of
Columbus water main lines through the project area, connecting two existing
lines.
ESTIMATED
SCHEDULE:
Design: Fall 2016 – Fall
2019
Right-of-way acquisition: Summer 2018-Fall 2019
Construction: Summer 2020 – Spring 2021, subject to funding approval by City
Council and weather conditions
ESTIMATED COSTS:
Design: $160,000
Right-of-way acquisition: $150,000
Utility relocation: $300,000
Construction: $2.1 million
CONTACT INFORMATION:
City of Columbus construction project manager: Phillip
Sekela, P.E, (614)
645-6530
Designer: E.P. Ferris & Associates, Inc.
Construction contractor: Strawser Paving Company