PID 105734
DESCRIPTION
AND BENEFITS:
This is the first
phase of a major widening project to construct new through and turn lanes of
various configurations in the East Broad Street corridor from the east side of
the I-270 interchange to the intersection of E. Broad Street and
Reynoldsburg-New Albany Road. This first phase will construct new pavement for
the widening and resurfacing of the existing pavement from the I-270
interchange to Outerbelt Street and will include traffic signal improvements;
addition of a shared use path, sidewalk, street lighting, street trees, signal
interconnect conduit; and incidental improvements such as drainage, traffic
control, sediment and erosion control, water adjustments, and maintenance of
traffic.
ESTIMATED SCHEDULE:
|
|
|
|
| PhASE | START | FINISH |
| Study | Fall 2017 | Spring 2020 |
| Design | Summer 2020 | Spring 2023 |
| Right-of-Way | Summer 2022 | Late 2023 |
| Utility
Relocations | Summer 2023 | Early 2024 |
| Construction | Early 2024* | Late 2025* |
*Subject
to funding approval by City Council and weather conditions
ESTIMATED
COSTS:
|
|
|
| PhASE | COST |
| Study | $400,000 |
| Design | $1.7 million |
| Right-of-Way | $2.2 million |
| Utility
Relocations | $100,000 |
| Construction | $16.0 million |
CONTACT INFORMATION:
|
|
|
| City of
Columbus Design Project Manager | Hannah
Webber, P.E., (614) 645-2859 |
| Designer | Transystems
Corporation |
| Construction
contractor | To be
determined |
VIRTUAL PUBLIC MEETING
A Virtual Public Meeting was held June 16, 2022 from 5:30-6:30 pm. A link to
the WebEx Webinar recording can be found below
Click Here to
view meeting recording
The following documents were shared at the public meeting and can be accessed
through the links below:
The public comment period will be open until Monday, July 18th,
2022. We have provided two ways to share comments: