This project scope consists of constructing sidewalks
along the south side of Kossuth Street from Carpenter Street to Linwood Avenue.
Installation of the sidewalk will include curb ramps, drive approaches, curb, retaining
walls, and may include stormwater drainage improvements in select areas.
Project will install 2600LF of sidewalks.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Summer 2018
|
Spring 2021
|
Right-of-Way |
Summer 2020
|
Spring 2021
|
Construction |
Fall 2021*
|
Summer 2022*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$230,000
|
Right-of-Way |
$80,000
|
Construction |
$1.2 million
|
CONTACT
INFORMATION:
City of Columbus Area
Engineer |
Tom Murphy, P.E., (614) 645-8455
|
Designer |
DLZ Ohio
|
Construction
contractor |
G&G Concrete
|