James Road at Livingston Ave

DESCRIPTION AND BENEFITS:

Project will construct right turn lanes from Livingston Avenue to James Road and replace traffic signals to accommodate additional turn lanes and improve intersection safety. Street lighting will be modified, and storm sewer capacity will be upgraded on Livingston Avenue.

ESTIMATED SCHEDULE:
Design: Early 2018 – Early 2020
Right-of-way acquisition: Spring 2019 – Spring 2020

Utility Relocation: Late 2019 – Summer 2020
Construction: Summer 2020 – Spring 2021, subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:
Design: $430,000 ($386,000 in ODOT Safety Funds)
Right-of-way acquisition: $321,000 ($286,000 in ODOT Safety Funds)

Utility relocation: $100,000 ($90,000 in ODOT Safety Funds)
Construction: $2.9 million ($2.3 million in ODOT Safety Funds)

CONTACT INFORMATION:

City of Columbus design project manager: Hannah Webber, P.E., (614) 645-2859
Designer: American Structurepoint
Construction contractor: To be determined