Avery Road Widening - Hayden Run Road to Lexi Lane/Castlefinn Lane
DESCRIPTION
AND BENEFITS:
This project will reconstruct and widen Avery Road from the
CSX railroad tracks to Avery Run Road.
There will be a roundabout at Avondale Woods Boulevard and a traffic
signal at the intersection of Lexi Lane and Castlefinn Drive. The reconstructed roadway will be converted
to a curb and gutter section with the addition of a 10’ wide shared use path
along the east side, sidewalk along the west side, street lighting, and street
trees. The anticipated lane configuration is two through lanes in each
direction with a two-way left turn lane or dedicated left turns at
intersections. The final traffic control configuration will be determined via
traffic analysis.
South of the railroad tracks, the existing roadway section
is not anticipated to be modified with the exception of lane control
modifications. Sidewalk will be extended south of the railroad tracks to
Winters Run Road. Other complete street improvements south of the tracks will
be determined in design following coordination with City of Hilliard and
Franklin County.
The project is also anticipated to include a waterline
extension along Avery Road, limits to be determined.
ESTIMATED
SCHEDULE:
PHASE
|
START
|
FINISH
|
Study
|
Late 2018
|
Late 2019
|
Design
|
Spring 2020
|
Fall 2024
|
Right-of-Way
|
Summer 2024
|
Fall 2025
|
Utility
Relocations
|
Fall 2024
|
Fall 2025
|
Construction
|
Fall 2025*
|
Late 2028*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE
|
COST
|
Study
& Design
|
$1.4 million
|
Right-of-Way
|
$200,000
|
Utility
Relocations
|
$300,000
|
Construction
|
$15.0 million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager
|
Tiffany Elchert, P.E., (614) 645-2923
|
Designer
|
Stantec, Inc.
|
Construction
contractor
|
To be determined
|