Avery Road Widening - Hayden Run Road to Lexi Lane/Castlefinn Lane

DESCRIPTION AND BENEFITS:

This project will reconstruct and widen Avery Road from the CSX railroad tracks to Avery Run Road.  There will be a roundabout at Avondale Woods Boulevard and a traffic signal at the intersection of Lexi Lane and Castlefinn Drive.  The reconstructed roadway will be converted to a curb and gutter section with the addition of a 10’ wide shared use path along the east side, sidewalk along the west side, street lighting, and street trees. The anticipated lane configuration is two through lanes in each direction with a two-way left turn lane or dedicated left turns at intersections. The final traffic control configuration will be determined via traffic analysis.

 

South of the railroad tracks, the existing roadway section is not anticipated to be modified with the exception of lane control modifications. Sidewalk will be extended south of the railroad tracks to Winters Run Road. Other complete street improvements south of the tracks will be determined in design following coordination with City of Hilliard and Franklin County.

 

The project is also anticipated to include a waterline extension along Avery Road, limits to be determined.


ESTIMATED SCHEDULE:

PHASE START FINISH
Study Late 2018 Late 2019
Design Spring 2020 Fall 2024
Right-of-Way Summer 2024 Fall 2025
Utility Relocations Fall 2024 Fall 2025
Construction Fall 2025* Late 2028*

*Subject to funding approval by City Council and weather conditions



ESTIMATED COSTS:

PHASE COST
Study & Design $1.4 million
Right-of-Way $200,000
Utility Relocations $300,000
Construction $15.0 million


CONTACT INFORMATION:

City of Columbus Design Project Manager Tiffany Elchert, P.E., (614) 645-2923
Designer Stantec, Inc.
Construction contractor To be determined