Arterial Street Rehabilitation – Hudson St – I-71 to Cleveland Ave

DESCRIPTION AND BENEFITS:

The project will reconstruct Hudson Street from I-71 to Cleveland Avenue. The reconstruction will include installing new curb, reconstruction and modification to the existing median on the east leg of the I-71 at Hudson intersection, sidewalk on the north side, a shared used path on the south side, street trees, new traffic signals, storm sewers, a new 24” water main, and new ADA curb ramps at intersections.

ESTIMATED SCHEDULE:

Design: Spring 2019 – Summer 2021
Right-of-way acquisition: Mid 2020 – Late 2021

Utility Relocation: Early 2021 – Fall 2021

Construction: Spring 2022 – Fall 2023, subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

Design: $1.6 million 
Right-of-way acquisition: $1.9 million

Utility Relocation: $1.0 million
Construction: $15.0 million

CONTACT INFORMATION:

City of Columbus design project manager: Hannah Webber, P.E., (614) 645-2859
Designer: American Structurepoint Inc.
Construction contractor: To be determined