Hudson Street Improvements - I-71 to Cleveland Avenue
DESCRIPTION
AND BENEFITS:
The project will reconstruct Hudson Street
from I-71 to Cleveland Avenue. The reconstruction will include installing new
curb, reconstruction and modification to the existing median on the east leg of
the I-71 at Hudson intersection, sidewalk on the north side, a shared used path
on the south side, street trees, new traffic signals, storm sewers, a new 24”
water main, and new ADA curb ramps at intersections.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Spring 2019
|
Fall 2021
|
Right-of-Way |
Summer 2020
|
Spring 2022
|
Utility
Relocations |
Late 2020
|
Spring 2022
|
Construction |
Summer 2022*
|
Summer 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$1.8 million
|
Right-of-Way |
$1.9 million
|
Utility
Relocations |
$1.0 million
|
Construction |
$19.4 million
|
CONTACT
INFORMATION:
City of Columbus Area
Engineer |
Jake Slechter, P.E., (614) 724-2625
|
Designer |
American Structurepoint Inc.
|
Construction
contractor |
Complete General Construction
|
VIRTUAL PUBLIC
MEETING
A virtual public meeting was held on Thursday,
October 22, 2020. A recording of the meeting can be found here
PROJECT
DOCUMENTS
Fact Sheet
ONE
Linden Area Projects
Vision
Zero Columbus
For information about the city's efforts to
eliminate all serious injury and fatal traffic crashes, please visit the Vision Zero Columbus webpage.