Maple Canyon Ave Sidewalks

DESCRIPTION AND BENEFITS:

This project will install sidewalk along the east side of Maple Canyon Ave from the existing sidewalk install at the Fire Station to Jewett Dr.  Sidewalk installation will include a combination of curbed and uncurbed ditch sections, drive approaches, curb ramps, and storm sewer.  Post construction BMP requirement will be installed.

ESTIMATED SCHEDULE:

Design: Spring 2019 – Fall 2020

Right-of-way acquisition:  Early 2020 – Fall 2020

Construction: Spring 2021 – Fall 2021, subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

Design: $250,000 
Right-of-way acquisition: $120,000

Construction: $1.4 million


CONTACT INFORMATION:

City of Columbus design project manager: Angela Fedak, P.E., (614) 645-3006
Designer: Resource International, Inc.