Maple Canyon Avenue Sidewalks - SR-161 to Jewett Drive
DESCRIPTION AND
BENEFITS:
This project will install sidewalk along the
east side of Maple Canyon Ave from the existing sidewalk install at the Fire
Station to Jewett Dr. Sidewalk installation will include a combination of
burn and uncurbed ditch sections, drive approaches, curb ramps, and storm
sewer. Post construction BMP requirement will be installed.
ESTIMATED SCHEDULE:
Design: Spring 2019 – Spring
2022
Right-of-way acquisition
Fall 2021 – Fall 2022
Construction: Spring
2022, subject to funding approval by City Council and weather conditions
ESTIMATED COSTS:
Design: $250,000
Right-of-way acquisition: $120,000
Construction: $1.4
million
CONTACT INFORMATION:
City of Columbus design project manager: Kevin Thomas, P.E., (614) 645-6470
Designer: Resource International, Inc.
Construction contractor: To
be determined