PID 104704
DESCRIPTION
AND BENEFITS:
This project consists
of the widening of Georgesville Road to provide a southbound right turn lane
onto Hall Road, widening of Hall Road to provide an eastbound right turn lane
onto Georgesville Road, and the full reconstruction of the traffic signal at
the intersection. In addition, a shared use path will be installed along the
south side of Hall Road from Durrow Drive (Private Street)/Georgesville Green
Drive to Georgesville Road. Where needed to accommodate the shared use path,
curb and gutter will be placed and a closed drainage system installed.
ESTIMATED
SCHEDULE:
PHASE
|
START
|
FINISH
|
Design
|
Fall 2019
|
Fall 2022
|
Right-of-Way
|
Fall 2022
|
Fall 2023
|
Utility
Relocations
|
Summer 2023
|
Early 2024
|
Construction
|
Early 2024*
|
Late 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE
|
COST
|
Design
|
$480,000.00
|
Right-of-Way
|
$230,000.00
|
Construction
|
$1.45 million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager
|
Kevin Thomas, P.E., (614) 645-6470
|
Designer
|
Mead & Hunt
|
Construction
contractor
|
To be determined
|