Sinclear Rd - Culvert
Project Scope: This project will
install new sidewalk along both sides of Sinclair Road from Morse Road to
Strimple Avenue. The project will also
replace the culvert over Bill Moose Run.
The culvert will be designed and replaced first while the sidewalk is
designed. The sidewalk will be installed
once the remaining design work is complete.
Estimated Costs:
- Design: $420,000
- Right-of-Way
Acquisition: $210,000
- Construction: $2.7
million
Current Status: in
Design
Schedule:
- Culvert Design: Completed
summer 2019
- Culvert Right of way: Completed
summer 2019
- Culvert Construction:
Begin summer 2019
- Sidewalk Design
Scheduled to finish in spring of 2020
- Sidewalk Right of Way:
Finish acquisition summer 2020
- Sidewalk Construction:
Begin Spring 2021
Contact Information:
- Design Project
Manager: Kevin Thomas tel (614) 645-6470
- Designer: Dynotec
- Culvert Contractor:
Complete General