Wilson Rd Shared-Use-Path
Project Scope: This project will
construct a shared-use path along the west side of Wilson road from Sullivant
Avenue to Broad Street. Connections will
also be made to Freemont Street. The
bridge deck on the structure over the Camp Chase Railroad will be replaced
along with this project as well. All of
the bridge work is being funded by Franklin County.
Estimated Costs:
- Design: Franklin
County funds - $132,580; City of Columbus funds - $267,420
- Right-of-Way
Acquisition: $30,000
- Construction: Franklin
County funds - $1,117,419; City of Columbus funds - $2,531,200
Current Status: In
Design
Schedule:
- Design: Complete
Summer 2019
- Right of way:
Acquisition Completed fall 2017
- Construction:
Begin Fall 2019
Contact Information:
- Design Project
Manager: Kevin Thomas tel (614) 645-6470
- Designer: Woolpert
- Contractor: To Be
Determied