Olive Street & Floral Ave Sidewalks
Operation Sidewalks – School Sidewalks – Hilltop (Olive Street and Floral Avenue)
Project Scope:
This project scope consists of constructing sidewalks along the south side of Olive Street from Powell Avenue to Harris Avenue, the north side of Olive from Harris to Wayne Avenue, and on the south side of Floral Avenue from Oakley Avenue to Highland Avenue. Installation of the sidewalk will include curb ramps and drive approaches and may include curb, curb walls, and stormwater drainage improvements in select areas.
Estimated Costs:
- Design: $270,670
- Right-of-Way
Acquisition: $90,000
- Construction: $1.5
million
Current Status: In
Design
Schedule:
- Design:
Scheduled to finish in Spring 2022
- Right of way: Finish
acquisition Spring 2023
- Construction:
Begin spring 2023
Contact Information:
- Design Project
Manager: Kevin Thomas tel (614) 645-6470
- Designer: Korda
- Contractor: To Be
Determined