Operation Sidewalks - School Sidewalks - Eastland (Refugee to Noe-Bixby)

Operation Sidewalks – School sidewalks – eastland (refugee road & noe bixby road)


Project Scope:
This project scope consists of constructing sidewalk along the north side of Refugee Road from Noe-Bixby Road to Blue Moon Drive and the south side of Refugee Road from Noe-Bixby Road to the existing sidewalk just west of Glenbriar Street. Installation of the sidewalk will include curb ramps, drive approaches, curb, and may include stormwater drainage improvements in select areas.  This project will also construct sidewalks along the east side of Noe-Bixby Road from Refugee Road to Carbondale Drive. Installation of the sidewalk will include curb ramps, intersection striping, signal improvements, and drive approaches.


Estimated Costs:

  • Design: $473,000
  • Right-of-Way Acquisition: $150,000
  • Construction: $2.4 million

Current Status: In Design


Schedule:

  • Design:  Scheduled to finish in spring 2022
  • Right of way: Finish acquisition Spring 2023
  • Construction:  Begin spring 2023


Contact Information:

  • Design Project Manager:  Kevin Thomas tel (614) 645-6470
  • Designer:  Toole Design Group
  • Contractor: To Be Determined