Operation Safewalks
DESCRIPTION
AND BENEFITS:
This project scope consists of constructing
sidewalk along the north side of Refugee Road from Noe-Bixby Road to Blue Moon
Drive and the south side of Refugee Road from Noe-Bixby Road to the existing
sidewalk just west of Glenbriar Street. Installation of the sidewalk will
include curb ramps, drive approaches, curb, and may include stormwater drainage
improvements in select areas.
ESTIMATED
SCHEDULE:
PhASE | START | FINISH |
Design |
Late 2018
|
Spring 2023
|
Right-of-Way |
Fall 2022
|
Fall 2023
|
Construction |
Late 2023*
|
Fall 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PhASE | COST |
Design |
$500,000
|
Right-of-Way |
$150,000
|
Construction |
$3.1 million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Hannah Webber, P.E., (614) 645-2859
|
Designer |
Toole Design Group
|
Construction
contractor |
To be determined
|