Design and Construction

Contact Information Department of Public Service
111 N. Front Street
Columbus, OH 43215
Office :  (614) 645-3111 
Fax :  (614) 645-7805 
Email : Contact Information

311 logo
(614) 645-3111

Operation Sidewalks - School Sidewalks - Eastland (Refugee to Noe-Bixby)

Project Scope: This project scope consists of constructing sidewalk along the north side of Refugee Road from Noe-Bixby Road to Blue Moon Drive and the south side of Refugee Road from Noe-Bixby Road to the existing sidewalk just west of Glenbriar Street. Installation of the sidewalk will include curb ramps, drive approaches, curb, and may include stormwater drainage improvements in select areas.  This project will also construct sidewalks along the east side of Noe-Bixby Road from Refugee Road to Carbondale Drive. Installation of the sidewalk will include curb ramps, intersection striping, signal improvements, and drive approaches.

Estimated Costs:

  • Design: $473,000
  • Right-of-Way Acquisition: $150,000
  • Construction: $2.4 million

Current Status: In Design

 Schedule:

  • Design:  Scheduled to finish in spring 2021
  • Right of way: Finish acquisition spring 2021
  • Construction:  Begin summer 2021

Contact Information:

  • Design Project Manager:  Kevin Thomas tel (614) 645-6470
  • Designer:  Toole Design Group
  • Contractor: To Be Determined