Celebrate One Sidewalks - Hilltop (Belvidere Ave)
Project Scope: This project scope
consists of constructing sidewalks along the west side of Belvidere Avenue from
Mound Street to Sullivant Avenue. Installation of the sidewalk will include
curb ramps and drive approaches. Existing sidewalk will be replaced where
needed.
Estimated Costs:
- Design: $118,900
- Right-of-Way
Acquisition: $15,000
- Construction: $480,000
Current Status: In
Design
Schedule:
- Design:
Scheduled to finish in fall 2019
- Right of way: Finish
acquisition fall 2019
- Construction:
Begin spring 2020
Contact Information:
- Design Project
Manager: Kevin Thomas tel (614) 645-6470
- Designer: AECOM
- Contractor: To Be
Determined