Cassady Avenue
improvements consist of the full reconstruction of the roadway to a 3-lane,
curb and gutter section with additional turn lanes at the intersection with E.
5th Avenue. Sidewalk will be placed along the east side and a shared use path
along the west side. Additional improvements include traffic signal
replacement, street lighting, street trees where feasible, and storm sewer.
Electric distribution and water line systems are anticipated to be impacted. The 12" water line between Avalon Place
and E. 5th Avenue will be replaced with a new 12" line.
E. 5th Avenue
improvements consist of roadway reconstruction with additional turn lanes at
the intersection with Cassady Avenue. The sidewalk will be replaced along both
sides and lighting and utility systems replaced/relocated as necessary.
Additional improvements include street lighting, street trees where feasible,
and storm sewer. Electric distribution and water line systems are anticipated
to be impacted. The water services from the existing 2" water line between
N. Dawson Avenue and Northview Avenue will be transferred to the existing
12" water line and the 2" line abandoned.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Study |
Spring
2018
|
Spring 2020
|
Design |
Spring 2020
|
Spring 2023
|
Right-of-Way |
Fall 2022
|
Spring 2024
|
Utility
Relocations |
Fall 2023
|
Early 2024
|
Construction |
Mid 2024*
|
Early 2026*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Study |
$530,000.00
|
Design |
$1.3 million
|
Right-of-Way |
$2.2 million
|
Utility
Relocations |
$200,000
|
Construction |
$9.4 million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Kevin Thomas, P.E., (614) 645-6470
|
Designer |
Woolpert
|
Construction
contractor |
To be determined
|