UIRF - PID 105732
DESCRIPTION
AND BENEFITS:
Cassady Avenue improvements consist of the full
reconstruction of the roadway to a 3-lane, curb and gutter section with
additional turn lanes at the intersection with E. 5th Avenue. Sidewalk will be
placed along the east side and a shared use path along the west side.
Additional improvements include traffic signal replacement, street lighting,
street trees where feasible, and storm sewer. Electric distribution and water
line systems are anticipated to be impacted. The 12" water line
between Avalon Place and E. 5th Avenue will be replaced with a new 12"
line.
E. 5th Avenue improvements consist of roadway
reconstruction with additional turn lanes at the intersection with Cassady
Avenue. The sidewalk will be replaced along both sides and lighting and utility
systems replaced/relocated as necessary. Additional improvements include street
lighting, street trees where feasible, and storm sewer. Electric distribution
and water line systems are anticipated to be impacted. The water services from
the existing 2" water line between N. Dawson Avenue and Northview Avenue
will be transferred to the existing 12" water line and the 2" line
abandoned.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Study |
Early 2018
|
Early 2020
|
Design |
Spring 2020
|
Fall 2023
|
Right-of-Way |
Fall 2022
|
Spring 2024
|
Utility
Relocations |
Spring 2022
|
Spring 2024
|
Construction |
Late 2024*
|
Summer 2026*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Study |
$530,000
|
Design |
$1.3 million
|
Right-of-Way |
$3.5 million
|
Utility
Relocations |
$200,000
|
Construction |
$11.0 million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Andrew Frankhouser, P.E, (614) 645-3006
|
Designer |
Woolpert
|
Construction
contractor |
To be determined
|