Worthington Woods Blvd - Shared Use Path

DESCRIPTION AND BENEFITS:

This project consists of approximately 7,700 feet of shared use path on the south/east side of Worthington Woods Boulevard from Sancus Boulevard to Park Road and along the south side of Park Road from Worthington Woods Blvd to Deer Creek Dr (northern intersection). In addition, sidewalk will be installed on the north side of Park Road from Worthington Woods Blvd to Deer Creek Drive.  Curb and gutter will be installed as needed where the available space between the edge of pavement and right-of-way does not allow for an open drainage system and SUP or sidewalk installation. Storm sewer facilities will also be installed in conjunction with the curb addition.   

ESTIMATED SCHEDULE:

Design: Spring 2020 – Spring 2021

Right-of-way acquisition: Fall 2020 – Fall 2021

Construction: Fall 2021 – Late 2022, subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

Design: $404,000 
Right-of-way acquisition: $400,000
Construction: $3.7 million

CONTACT INFORMATION:

City of Columbus design project manager: Angela Fedak, P.E., (614) 645-3006
Designer: Strand Associates, Inc.

Construction contractor: To be determined