Worthington Woods Blvd Shared Use Path - Sancus Blvd to Park Road
DESCRIPTION
AND BENEFITS:
This project consists
of approximately 7,700 feet of shared use path on the south/east side of
Worthington Woods Boulevard from Sancus Boulevard to Park Road and along the
south side of Park Road from Worthington Woods Blvd to Deer Creek Dr (northern
intersection). In addition, sidewalk will be installed on the north side of
Park Road from Worthington Woods Blvd to Deer Creek Drive. Curb and
gutter will be installed as needed where the available space between the edge
of pavement and right-of-way does not allow for an open drainage system and SUP
or sidewalk installation. Storm sewer facilities will also be installed in
conjunction with the curb addition.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Spring 2020
|
Fall 2022
|
Right-of-Way |
Spring 2021
|
Spring 2023
|
Utility
Relocations |
Summer 2022
|
Fall 2022
|
Construction |
Summer 2023*
|
Summer 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$404,000
|
Right-of-Way |
$350,000
|
Construction |
$2.9 Million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Andrew Frankhouser, P.E., (614) 645-3006
|
Designer |
Strand Associates Inc.
|
Construction
contractor |
To Be Determined
|