Design and Construction

Contact Information Department of Public Service
111 N. Front Street
Columbus, OH 43215
Office :  (614) 645-3111 
Fax :  (614) 645-7805 
Email : Contact Information

311
(614) 645-3111

Cleveland Avenue Pedestrian Improvements (PID108642)

CLEVELAND AVENUE PEDESTRIAN IMPROVEMENTS (PID108642)

DESCRIPTION AND BENEFITS:


The project includes pedestrian improvements at seven intersections along Cleveland Avenue: Camden Avenue, E. 19th Avenue, Kenmore Road, Republic Avenue, Lakeview Avenue, Agler Road, and Lehner Road. Improvements consist of the installation of enhanced crosswalk markings, the installation of Rectangular Rapid Flashing Beacons (RRFB’s) or Pedestrian Hybrid Beacons (PHB’s) at each intersection and installation of new ADA-compliant curb ramps. Minimal pavement resurfacing is required where enhanced crosswalks are being installed and signage/striping will be updated to accommodate these improvements.

Public Involvement:

Project notification documents were distributed by the City and their consultant team consisting of an informational flyer posted at public locations, a notification letter mailed to property owners and residents within the project area, and a comment form for issuing comments. Those documents may be downloaded at the links below. Comments were accepted until October 29, 2021.

Cleveland Avenue Flyer
Cleveland Avenue Public Notice

The City received a total of 7 responses during the public comment period which included 22 unique comments and questions. These were consolidated into 13 questions and comments. A response document was sent to everyone who submitted a comment and is also available for download below:

Cleveland Avenue Comment Response Letter

Public Meeting Information:

A public meeting will also be held at the St. Stephen’s Community House at 1500 E 17th Avenue on May 24th at 11:30am-1pm and 6pm-7:30pm. A presentation will be given in person with an online option available 30 minutes after the meeting start time for both the lunch and evening sessions. Postcards, flyers, and pamphlets were distributed to businesses and residents in the area. Digital copies are available below

Cleveland Avenue Open House Flyer
Cleveland Avenue Open House Flyer(Spanish)
Cleveland Avenue Open House Flyer (Somali)

Cleveland Avenue Open House Postcard
Cleveland Avenue Open House Postcard(Spanish)
Cleveland Avenue Open House Postcard(Somali)

Cleveland Avenue Open House Pamphlet 
Cleveland Avenue Open House Pamphlet (Spanish)
Cleveland Avenue Open House Pamphlet(Somali)

To join the virtual public meeting on May 24th at either meeting time click the link below:
(Link coming soon)

ESTIMATED SCHEDULE:
Design: Fall 2020 – Summer 2022
Right-of-way acquisition: Winter 2021/2022 – Winter 2022/2023
Utility Relocation: Spring 2022 – Spring 2023
Construction: Summer 2023 – Winter 2023/2024

ESTIMATED COSTS:
Design: $500,000 ($414,000 provided by ODOT)
Right-of-way acquisition: $300,000 ($270,000 provided by ODOT)
Utility Relocation: $0
Construction: $1,150,000 ($1,026,000 provided by ODOT)

CONTACT INFORMATION:
City of Columbus design project manager: Steve Schmidt, P.E., (614) 645-396
Designer: Carpenter Marty Transportation Inc.
Construction contractor: To be determined