DESCRIPTION AND BENEFITS:

This is the second phase of a major widening project to construct new through and turn lanes of various configurations in the East Broad Street corridor from the east side of the I-270 interchange to the intersection of E. Broad Street and Reynoldsburg-New Albany Road. This second phase will construct new pavement for the widening and resurfacing of the existing pavement from Outerbelt Street to Reynoldsburg-New Albany Road and will include traffic signal improvements; addition of a shared use path, sidewalk, street lighting, street trees, signal interconnect conduit; and incidental improvements such as drainage, traffic control, sediment and erosion control, water adjustments, and maintenance of traffic.

ESTIMATED SCHEDULE:


PHASESTARTFINISH
Study Summer 2020 Spring 2022
Design Early 2023 Early 2026
Right-of-Way Fall 2024 Early 2026
Utility Relocations Fall 2024 Early 2026
Construction Spring 2026* Fall 2027*

*Subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

PHASECOST
Study $500,000
Design $1.9 million
Right-of-Way $1.3 million
Utility Relocations $400,000
Construction $16.2 million

CONTACT INFORMATION:

City of Columbus Design Project Manager Hannah Webber, P.E., (614) 645-2859
Designer Burgess & Niple
Construction contractor To be determined


VIRTUAL PUBLIC MEETING

A Virtual Public Meeting was held on January 27, 2022 from 5:30-6:30 pm. A link to the WebEx Event recording can be found below:

Click Here
 to view meeting recording

The following documents were shared at the public meeting and can be accessed through the links below:

The public comment period was open until Monday, February 28th, 2022.  A summary of responses to the comments received can be accessed through the link below: