Summit Street Signals Phase 1 - Warren Street to 7th Avenue
DESCRIPTION
AND BENEFITS:
This project scope consists of replacing and
upgrading to current standards the existing traffic signals along Summit Street
from Warren Street to E. 7th Ave. This includes intersections of
Summit St. with N. 3rd St./Warren St., E. 1st Ave., E. 2nd Ave., E. 5th Ave., and
E. 7th Ave.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Fall 2020
|
Early 2023
|
Right-of-Way |
Fall 2021
|
Early 2023
|
Utility
Relocations |
Spring 2022
|
Early 2023
|
Construction |
Spring 2023*
|
Spring 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$600,000
|
Right-of-Way |
$100,000
|
Utility
Relocations |
$50,000
|
Construction |
$3.5 million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Hannah Webber, P.E., (614) 645-2859
|
Designer |
ms consultants
|
Construction
contractor |
To be determined
|