Summit Street Signals Phase 2 - Chittenden Ave to Hudson Street
DESCRIPTION
AND BENEFITS:
This project consists of the design of a
replacement and upgrade to current standards of the existing traffic signals
along Summit Street from Chittenden Avenue to Hudson Street, excluding the
signal at 17th Avenue. This includes the intersections of Summit St. with
Chittenden Ave., E. 12th Ave., E. 15th Ave., E. Lane Ave., and E. Hudson St.
ESTIMATED
SCHEDULE:
PHASE
|
START
|
FINISH
|
Design
|
Summer 2021
|
Spring 2023
|
Right-of-Way
|
Fall 2021
|
Late 2023
|
Utility
Relocations
|
Fall 2023
|
Late 2023
|
Construction
|
Spring 2024*
|
Spring 2025*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE
|
COST
|
Design
|
$600,000
|
Right-of-Way
|
$100,000
|
Utility
Relocations
|
$50,000
|
Construction
|
$3.0 million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager
|
Hannah Webber, P.E., (614) 645-2859
|
Designer
|
TEC Engineering, Inc.
|
Construction
contractor
|
To be determined
|
City of Columbus
Design Project Manager
|
Hannah Webber, P.E., (614) 645-2859
|
Designer
|
TEC Engineering, Inc.
|
Construction
contractor
|
To be determined
|