Summit Street Signals Phase 2 - Chittenden Ave to Hudson Street

DESCRIPTION AND BENEFITS:

 

This project consists of the design of a replacement and upgrade to current standards of the existing traffic signals along Summit Street from Chittenden Avenue to Hudson Street, excluding the signal at 17th Avenue. This includes the intersections of Summit St. with Chittenden Ave., E. 12th Ave., E. 15th Ave., E. Lane Ave., and E. Hudson St.

 

ESTIMATED SCHEDULE:

 

PHASE START FINISH
Design Summer 2021 Spring 2023
Right-of-Way Fall 2021 Late 2023
Utility Relocations Fall 2023 Late 2023
Construction Spring 2024* Spring 2025*

*Subject to funding approval by City Council and weather conditions

 

ESTIMATED COSTS:

 

PHASE COST
Design $600,000
Right-of-Way $100,000
Utility Relocations $50,000
Construction $3.0 million



CONTACT INFORMATION:

 

City of Columbus Design Project Manager Hannah Webber, P.E., (614) 645-2859
Designer TEC Engineering, Inc.
Construction contractor To be determined