Bikeway Development – Tussing Road SUP Brice Rd to Hines Rd

DESCRIPTION AND BENEFITS:

This project will add a shared-use path along Tussing Road from Brice Road to Hines Road. The purpose of this project is to improve the quality and connectivity of bikeways in the City of Columbus by providing infrastructure that encourages and enables citizens to ride their bike or walk along Tussing Road.

 

ESTIMATED SCHEDULE:

Design: Fall 2021 – Fall 2022
Right-of-way acquisition: Summer 2022 – Summer 2023

Utility Relocations: Summer 2022 – Summer 2023
Construction: Late 2023 – Late 2024, subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

Design: $700,000 
Right-of-way acquisition: $250,000
Construction: $2.9 million

CONTACT INFORMATION:

City of Columbus design project manager: Hannah Webber, P.E., (614) 645-2859
Designer: Dynotec, Inc.
Construction contractor: To be determined