Celebrate1, Blueprint Linden
DESCRIPTION
AND BENEFITS:
This project scope consists of constructing sidewalks
along the west side of Dresden Street from East Hudson Street to Weber Road,
and along the west side of Medina Avenue from Linden Park Drive to Weber Road.
Installation of the sidewalk will include curb ramps, drive approaches, curb, retaining
walls, and may include stormwater drainage improvements in select areas.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Early 2019
|
Late 2022
|
Construction |
Summer 2023*
|
Late 2025*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$100,000
|
Construction |
$1.5 million
|
CONTACT
INFORMATION:
City of Columbus Design
Project Manager |
Hannah Webber, P.E., (614) 645-2859
|
Designer |
Gresham Smith & Partners
|
Construction
contractor |
To be determined
|