Hamilton Rd from SR161 to Central College Rd

DESCRIPTION AND BENEFITS:

This project is currently in the study phase of a project that will widen Hamilton Road from SR161 to Central College Road. Improvements include the SR161 interchange intersections on the east side of Hamilton Road.  In addition, a shared use path will be installed on the east side of the roadway. 

 

ESTIMATED SCHEDULE:

Study: Summer 2020 – Late 2021

Design: Early 2022 – Spring 2023

Right-of-way acquisition: Late 2022 – Early 2024

Construction: Spring 2024 – Fall 2025, subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

Design: $1.8 million

Right-of-way acquisition: $200,000
Construction: $19.0 million

CONTACT INFORMATION:

City of Columbus design project manager: Hannah Webber, P.E., (614) 645-2859
Designer: American Structurepoint

Construction contractor: To be determined