Hamilton Road (North) Phase C Widening - Dublin Granville Road to Central College Road
DESCRIPTION
AND BENEFITS:
This project will widen Hamilton Road from SR161
to Central College Road and install roundabouts along Hamilton Road at
Heathland Lane/Walton Breck Way and at Warner Road. The project will also
include a shared-use path to be installed on the east side of Hamilton Road
from Dublin-Granville Road to Central College Road, with a sidewalk on the west
side of Hamilton Road from Dublin-Granville Road to Central College Road. Additionally,
the project will include street lighting and associated stormwater drainage
improvements
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Study |
Summer
2020
|
Early
2023
|
Design |
Spring
2023
|
Summer
2024
|
Right-of-Way |
Spring
2024
|
Spring
2025
|
Utility
Relocations |
Late
2023
|
Spring
2025
|
Construction |
Summer
2025*
|
Late
2026*
|
ESTIMATED COSTS:
PHASE | COST |
Study |
$500,000
|
Design |
$1.3 Million
|
Right-of-Way |
$200,000
|
Construction |
$19.1 Million
|
CONTACT INFORMATION:
City of Columbus Design Project Manager: S. Eric Lambert, P.E., (614) 645-2732
Designer: American Structurepoint
Construction contractor: To be determined
VIRTUAL PUBLIC
MEETING
A
Virtual Public Meeting was held March 3, 2022 from 5:30-6:30 pm. A link to the
WebEx Event recording can be found here.
The
PowerPoint presentation that was shared at the public meeting can be found at
the link below:
Hamilton
Road Improvements – SR 161 to Central College Road – Public Meeting PowerPoint
Presentation
The comment period will be
open for 30 days, until April 4th, 2022. You can comment directly through the
link below:
https://survey.alchemer.com/s3/6756515/Hamilton-Road-Improvements