Hamilton Road (North) Phase C Widening - Dublin Granville Road to Central College Road
DESCRIPTION
AND BENEFITS:
This project is currently in the study phase
of a project that will widen Hamilton Road from SR161 to Central College Road.
Improvements include the SR161 interchange intersections on the east side of
Hamilton Road. In addition, a shared use
path will be installed on the east side of the roadway.
ESTIMATED
SCHEDULE:
Study: Summer 2020 – Summer 2022
Design: Summer 2022 – Summer 2024
Right-of-way acquisition: Late 2023 – Late 2024
Construction: Spring 2025 – Late 2026, subject
to funding approval by City Council and weather conditions
ESTIMATED COSTS:
Design: $1.8 million
Right-of-way acquisition: $500,000 - $1.0
Million
Utility Relocation: TBD in Design
Construction: $15-18 million
CONTACT INFORMATION:
City of Columbus design project manager: Hannah Webber, P.E., (614) 645-2859
Designer: American Structurepoint
Construction contractor: To be determined
VIRTUAL PUBLIC
MEETING
A
Virtual Public Meeting was held March 3, 2022 from 5:30-6:30 pm. A link to the
WebEx Event recording can be found here.
The
PowerPoint presentation that was shared at the public meeting can be found at
the link below:
Hamilton
Road Improvements – SR 161 to Central College Road – Public Meeting PowerPoint
Presentation
The comment period will be
open for 30 days, until April 4th, 2022. You can comment directly through the
link below:
https://survey.alchemer.com/s3/6756515/Hamilton-Road-Improvements