SR 161 at Karl Road Intersection Improvements
PID# 110436
DESCRIPTION
AND BENEFITS:
This
is the second project along the SR 161 from I-71 to Cleveland Ave
corridor. This safety portion of this project will add a mini roundabout
and median along the northern approach of the intersection of Karl Rd with SR
161 and install pedestrian facilities along the roadway. The traffic signal at
this intersection will also be reconstructed to accommodate these modifications
as part of the safety project.
ESTIMATED
SCHEDULE:
Design:
Fall 2019 – Spring 2021
Right-of-way
acquisition: Early 2021 – Early 2022
Construction:
Begins Spring 2022, subject to funding approval by City Council and weather
conditions
ESTIMATED COSTS:
Design:
$430,000
Right-of-way
acquisition: $175,000
Construction:
$2,400,000
CONTACT INFORMATION:
City of Columbus design project manager: Tiffany Elchert, P.E., (614) 645-2923
Designer:
IBI Group
Construction
contractor: To be determined