Contact Information
Department
of Public Service
111 N. Front Street
Columbus,
OH 43215
Office : (614)
645-3111
Fax : (614)
645-7805
Email : Contact Information

(614) 645-3111
SR 161 Phase 2 - Tamarack Blvd, Sharon Woods Blvd, Beechcroft Road
Project Scope:
This project involves the preliminary engineering and detailed design
plans for the SR161 corridor between I-71 and Cleveland Avenue. This second
phase will provide Improvements to SR161 from Maple Canyon Avenue to Ambleside
Dr. Side streets including Beechcroft Rd and Tamarack/Sharon Woods Blvd will be
improved north and south of SR161. These improvements will include the addition
of pedestrian and bike facilities, new traffic signals, pavement widening and
resurfacing, raised medians on the side streets and the installation of
mini-roundabouts. The SUP Limits will be
from Maple Canyon Ave to Ambleside Dr.
Estimated Costs:
Design: $1,450,000
Right-of-way acquisition: 1,100,000
Construction: 12,650,000
Tentative Schedule:
Design: 2022 –2024
Right-of-way acquisition: 2025
Construction: 2026
Contact Information:
City of Columbus Design Project Manager: Tiffany Elchert, tel. (614)
645-2923
Designer: IBI Group
Construction Contractor: TBD