Arterial street rehabilitation - SR161 - I71 to Cleveland Avenue Phase 2
Arterial street rehabilitation -
SR161 - I71 to Cleveland Avenue Phase 2
This project involves the preliminary engineering and detailed design
plans for the SR161 corridor between I-71 and Cleveland Avenue. This second
phase will provide Improvements to SR161 from Maple Canyon Avenue to Ambleside
Dr. Side streets including Beechcroft Rd and Tamarack/Sharon Woods Blvd will be
improved north and south of SR161. These improvements will include the addition
of pedestrian and bike facilities, new traffic signals, pavement widening and
resurfacing, raised medians on the side streets and the installation of
mini-roundabouts. The SUP Limits will be
from Maple Canyon Ave to Ambleside Dr.
Estimated Costs:
Design: $1,450,000
Right-of-way acquisition: 1,100,000
Construction: 12,650,000
Tentative Schedule:
Design: 2022 –2024
Right-of-way acquisition: 2025
Construction: 2026
Contact Information:
City of Columbus Design Project Manager: Tiffany Elchert, tel. (614)
645-2923
Designer: IBI Group
Construction Contractor: TBD