DESCRIPTION
AND BENEFITS:
The project consists of improvements at the
intersection of Hocking Street at US33 and Hanover Street at US33. At Hocking
Street, the eastbound left turn on Long Street will be widened to a double left
turn lane. The intersection of Hocking at Spring Street will be signalized. At
Hanover Street, both Hanover at Long Street and Hanover at Spring Street will
be signalized. The eastbound left turn on Long Street will be removed and the
section of Hanover Street between Long Street and Spring Street will be
converted to one-way southbound. Hocking and Hanover will be restriped between
Spring Street and Nationwide Boulevard.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Summer 2020
|
Early 2023
|
Right-of-Way |
Early 2022
|
Early 2023
|
Utility
Relocations |
Spring 2022
|
Spring 2023
|
Construction |
Summer 2023*
|
Summer 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$125,000
|
Right-of-Way |
$30,000
|
Construction |
$700,000
|
CONTACT
INFORMATION:
City of Columbus Construction
Project Manager |
Scott Roe, (614) 645-0431
|
Designer |
GPD Inc.
|
Construction
contractor |
Danbert Electric Corporation
|