GEORGESVILLE ROAD SHARED-USE-PATH
Georgesville Road SHARED-USE-PATH
Project Scope: This project consists of installing a new
shared use path (SUP) along the east side of Georgesville Road from Parkwick
Drive to Sullivant Avenue (south leg, west of Georgesville). In addition to the
SUP, the project will install curb ramps, drive aprons, and curb and storm
sewer as needed. The project crosses a bridge over Scioto Big Run that will
require modification to accommodate a 10' SUP. Stormwater control facilities
will be upgraded as required.
Estimated Costs:
- Design: $250,000
- Right-of-Way Acquisition:
$200,000
- Construction: $1,600,000
Current
Status: In Design
Schedule:
- Design: Scheduled
to finish in spring 2023
- Right of way: Finish
acquisition fall 2023
- Construction:
Begin Spring 2024
Contact Information:
- Design Project
Manager: Kevin Thomas tel (614) 645-6470
- Designer: E.L.
Robinson
- Contractor: To Be
Determined