Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue
DESCRIPTION
AND BENEFITS:
This project consists of installing a new shared use path
(SUP) along the east side of Georgesville Road from Parkwick Drive to Sullivant
Avenue (south leg, west of Georgesville). In addition to the SUP, the project
will install curb ramps, drive aprons, sidewalk along the west side of
Georgesville Road at select locations, street lighting, and curb and storm
sewer as needed. This project will also install sidewalk and curb ramps
along the north side of Parkwick Drive to fill gaps between Georgesville Road
and Bay club Drive. The striping configuration and pavement width at the
bridge over Scioto Big Run will be modified to provide a narrower roadway
section in order to accommodate a shared use path along the east side and
sidewalk along the west side. Additionally, Georgesville Road will be
resurfaced from the north side of the Georgesville Road bridge over IR-270 to
the City of Columbus corporation limit north of Camp Chase Railroad
crossing.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Early 2023
|
Late 2024
|
Right-of-Way |
Summer 2023
|
Late 2024
|
Utility
Relocations |
Late 2023
|
Late 2024
|
Construction |
Summer 2025
|
Spring 2026
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$750,000
|
Construction |
$3,200,000
|
Right of
Way |
$150,000
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Andrew Frankhouser, P.E., (614) 645-3006
|
Designer |
E.L Robinson Engineering
|
Construction
contractor |
To be determined
|