Barnett Road Sidewalks - Astor Ave to Main St
DESCRIPTION
AND BENEFITS:
The project scope
consists of constructing sidewalks along the east side of Barnett Rd from Astor
Ave to Main St. The installation of the sidewalk will include curb ramps, drive
approaches, resurfacing, and may include storm water drainage improvements in select
areas as well as incidental improvements traffic control, and maintenance of
traffic.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Study |
Spring 2022
|
Fall 2022
|
Design |
Fall 2022
|
Fall 2023
|
Right-of-Way |
Summer 2023
|
Summer 2024
|
Utility
Relocations |
Fall 2023
|
Fall 2024
|
Construction |
Fall 2024
|
Late 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$250,000
|
Right-of-Way |
$50,000
|
Construction |
$850,000
|
CONTACT
INFORMATION:City of Columbus Design
Project Manager |
Andrew Frankhouser, P.E., (614) 645-3006
|
Designer |
VS Engineering, Inc.
|
Construction
contractor |
To be determined
|