DESCRIPTION AND BENEFITS:


The project scope consists of constructing sidewalks along the east side of Barnett Rd from Astor Ave to Main St. The installation of the sidewalk will include curb ramps, drive approaches, resurfacing, and may include storm water drainage improvements in select areas as well as incidental improvements traffic control, and maintenance of traffic.

ESTIMATED SCHEDULE:

PHASE START FINISH
Study Spring 2022 Fall 2022
Design Fall 2022 Fall 2023
Right-of-Way Summer 2023 Summer 2024
Utility Relocations Fall 2023 Fall 2024
Construction Fall 2024 Late 2024*

*Subject to funding approval by City Council and weather conditions

 

ESTIMATED COSTS:

 

PhASE COST
Design $250,000
Right-of-Way $50,000
Construction $850,000


CONTACT INFORMATION:

 

City of Columbus Design Project Manager Andrew Frankhouser, P.E., (614) 645-3006
Designer VS Engineering, Inc.
Construction contractor To be determined