The project scope consists of constructing sidewalks along
the east side of Barnett Rd from Astor Ave to Main St. The installation of the
sidewalk will include curb ramps, drive approaches, resurfacing, and may
include storm water drainage improvements in select areas as well as incidental
improvements traffic control, and maintenance of traffic.
ESTIMATED
SCHEDULE:
PHASE
|
START
|
FINISH
|
Design
|
Early 2023
|
Summer 2024
|
Right-of-Way
|
Spring 2024
|
Spring 2025
|
Construction
|
Summer 2025*
|
Spring 2026*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE
|
COST
|
Design
|
$250,000
|
Right-of-Way
|
$50,000
|
Construction
|
$850,000
|
CONTACT
INFORMATION:
City of Columbus Construction
Project Manager
|
Andrew Frankhouser, P.E, (614) 645-3006
|
Designer
|
VS Engineering, Inc.
|
Construction
contractor
|
To Be Determined
|