The project scope
consists of constructing sidewalks along the east side of Barnett Rd from Astor
Ave to Main St. The installation of the sidewalk will include curb ramps, drive
approaches, resurfacing, and may include storm water drainage improvements in
select areas as well as incidental improvements traffic control, and
maintenance of traffic.
ESTIMATED
SCHEDULE:
PHASE
|
START
|
FINISH
|
Study
|
Spring 2022
|
Fall 2022
|
Design
|
Fall 2022
|
Fall 2023
|
Right-of-Way
|
Summer 2023
|
Summer 2024
|
Utility
Relocations
|
Fall 2023
|
Fall 2024
|
Construction
|
Fall 2024
|
Late 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PhASE
|
COST
|
Design
|
$250,000
|
Right-of-Way
|
$50,000
|
Construction
|
$850,000
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager
|
Andrew Frankhouser, P.E., (614) 645-3006
|
Designer
|
VS Engineering, Inc.
|
Construction
contractor
|
To be determined
|