DESCRIPTION
AND BENEFITS:
The project scope
consists of the installation of a traffic signal at the intersection of
Lockbourne Rd with Obetz Rd. This includes the installation of curb ramps,
walks, and necessary signing and pavement markings for the new traffic signal.
ESTIMATED
SCHEDULE:
PhASE | START | FINISH |
Design |
Summer 2022
|
Summer 2023
|
Right-of-Way |
Summer 2023
|
Summer 2024
|
Utility
Relocations |
Summer 2023
|
Summer 2024
|
Construction |
Summer 2024*
|
Late 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PhASE | COST |
Design |
$100,000
|
Construction |
$600,000
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Andrew Frankhouser, P.E., (614) 645-3006
|
Designer |
E.P. Ferris and Associates
|
Construction
contractor |
To be determined
|
City of Columbus
Design Project Manager |
Andrew Frankhouser, P.E., (614) 645-3006
|
Designer |
E.P. Ferris and Associates
|
Construction
contractor |
To be determined
|