DESCRIPTION
AND BENEFITS:
The project scope consists of the installation of a traffic
signal at the intersection of Lockbourne Rd with Obetz Rd. This includes the
installation of curb ramps, walks, and necessary signing and pavement markings
for the new traffic signal.
ESTIMATED
SCHEDULE:
PhASE | START | FINISH |
Design |
Summer 2022
|
Early 2024
|
Right-of-Way |
Spring 2023
|
Spring 2024
|
Utility Relocations |
Summer 2023
|
Spring 2024
|
Construction |
Summer 2024*
|
Fall 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$100,000
|
Construction |
$800,000
|
CONTACT
INFORMATION:
City of Columbus Construction
Project Manager |
Andrew Frankhouser, P.E, (614) 645-3006
|
Designer |
E.P Ferris &
Associates
|
Construction
contractor |
To be determined
|