Astor Park Streetscape Phase 1

DESCRIPTION AND BENEFITS:

The project includes sidewalk and streetscape improvements in the Astor Park area along Neiland Drive, Nordecke Drive, Columbus Crew Way and Nationwide Boulevard. Streetscape improvements consist of raised planters with street trees and ground cover, a combination of concrete and paver sidewalk, and street furnishings. Roadway improvements and utilities previously installed with the new roadways will remain.

ESTIMATED SCHEDULE:

PhASESTARTFINISH
Design Spring 2022 Spring 2023
Right-of-Way Spring 2023 Late 2023
Construction Early 2023* Late 2023*

*Subject to funding approval by City Council and weather conditions

 

ESTIMATED COSTS:

PhASECOST
Design $150,000
Right-of-Way $0  
Construction $2.5 million

   

CONTACT INFORMATION:

 
City of Columbus Design Project Manager Steve Schmidt, P.E., (614) 645-3966
Designer OHM Advisors
Construction contractor To be determined