Design and Construction

Contact Information Department of Public Service
111 N. Front Street
Columbus, OH 43215
Office :  (614) 645-3111 
Fax :  (614) 645-7805 
Email : Contact Information

311
(614) 645-3111

DESCRIPTION AND BENEFITS:

The project scope consists of the replacement of traffic signals at the intersections of 4th St with 1st Ave, 2nd Ave, 5th Ave, 7th Ave, and 17th Ave. This will include traffic signal improvements, and incidental improvements such as sidewalk, curb ramps, street lighting, traffic control, and maintenance of traffic

ESTIMATED SCHEDULE:

PHASESTARTFINISH
Design Spring 2023 Summer 2024
Right-of-Way Spring 2024 Spring 2025
Utility Relocations Spring 2025 Spring 2025
Construction Summer 2025* Summer 2026*

*Subject to funding approval by City Council and weather conditions


ESTIMATED COSTS:

PHASECOST
Design $750,000
Right-of-Way $150,000
Construction $3.5 Million



CONTACT INFORMATION:

City of Columbus Design Project Manager Andrew Frankhouser, P.E., (614) 645-3006
Designer 2LMN,  Inc.
Construction contractor To Be Determined