DESCRIPTION
AND BENEFITS:
The project scope
consists of the replacement of traffic signals at the intersection of Rich St.
with 3rd St., 4th St., 5th St., and Grant Ave.
This will include traffic signal improvements, sidewalk, curb, street lighting,
and incidental improvements such as drainage, traffic control, and maintenance
of traffic.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Fall 2022
|
Summer 2024
|
Right-of-Way |
Late 2023
|
Late 2024
|
Utility
Relocations |
Fall 2023
|
Fall 2024
|
Construction |
Summer 2025*
|
Early 2027*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$460,000
|
Right-of-Way |
$100,000
|
Utility
Relocations |
$40,000
|
Construction |
$3.1 Million
|
CONTACT
INFORMATION:
City of Columbus Construction
Project Manager |
Andrew Frankhouser, P.E, (614) 645-3006
|
Designer |
Lanham Engineering
|
Construction
contractor |
To be determined
|