DESCRIPTION AND BENEFITS:

The project scope consists of the replacement of traffic signals at the intersection of Rich St. with 3rd St., 4th St., 5th St., and Grant Ave. This will include traffic signal improvements, sidewalk, curb, street lighting, and incidental improvements such as drainage, traffic control, and maintenance of traffic.

ESTIMATED SCHEDULE:

PHASESTARTFINISH
Design Fall 2022 Summer 2024
Right-of-Way Late 2023 Late 2024
Utility Relocations Fall 2023 Fall 2024
Construction Summer 2025* Early 2027*

*Subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:
 

PHASECOST
Design $460,000
Right-of-Way $100,000
Utility Relocations $40,000
Construction $3.1 Million

CONTACT INFORMATION:

City of Columbus Construction Project Manager Andrew Frankhouser, P.E, (614) 645-3006
Designer Lanham Engineering
Construction contractor To be determined