Arbor Hill Drive and Gypsy Lane Roadway Improvements
Scope: This project consists of pavement reconstruction of
Arbor Hill Drive from approximately 130' west of the Harrington Drive
centerline to just east of the storm sewer crossings at the intersection of
Arbor Hill and Harrington. There will also be the addition of four new curb
ramps on Arbor Hill Drive. The second portion of this project consist of
reconstructing Gypsy Lane starting approximately 180' west of the Peardale Road
centerline and continuing to a point approximately 170' west of the starting point
and relocating two inlets.
Design Cost: $95,000
Construction Cost: $150,000
Construction Year : 2017
Project Manager: Kyle Hardy, (614) 645-2732