Lazelle Road Improvements

Description:

The city of Columbus and the Ohio Department of Transportation (ODOT) are collaborating to improve Lazelle Road between High Street and Worthington-Galena Road. The project will be done in three phases and widen parts of Lazelle Road to accommodate the addition of left-turn lanes and include other upgrades to improve safety for pedestrians and bicyclists. The project is subject to the availability of funding, and will include:

Lazelle Phase A & B: US 23 to Sancus Boulevard including roundabout at South Old State Road

Reconstruction of roadway and widening Lazelle Road for additional lanes.

  • 2 EB & 2 WB lanes with a center turn lane east of the roundabout.

  • 1 EB & 1 WB lane with a center turn lane west of the roundabout.

Relocation of South Old State Road at its intersection with Lazelle Road including construction of a roundabout.

Reconstruction of the CSX & Norfolk Southern railroad bridges over Lazelle Road.

Installation of a new traffic signal at the Flint Road & Lazelle Road intersection.

Addition of sidewalks on the south side and a shared-use path on the north side of Lazelle Road in addition to curbs, gutters, and curb ramps.

New drainage, pavement markings, street lighting, and landscaping.

Project Cost: $22.6 million

Contractor: Shelly & Sands

Construction Start:  Spring 2019

Completion Date: September 30, 2021

 

Lazelle Phase C: Sancus to Worthington-Galena

Reconstruction of roadway and widening Lazelle Road for additional lanes.

    1 EB & 1 WB lane with a center turn lane between Sancus Blvd & WOrthington Galena Rd

    Addition of sidewalks on the south side and a shared-use path on the north side of Lazelle Road in addition to curbs, gutters, and curb ramps.

    New drainage, pavement markings, street lighting, and landscaping.

    Project Cost: $5.2 million

    Contractor: Double Z Construction

    Completion Date: September 30, 2021

       

      Contact Information:

      Construction Project Manager:  Evan Bell, (614) 645-0989

      Design Project Manager:  Cristina Parady, (614) 645-5463

      Designer: Gannett Fleming Engineers and Architects

      Construction Contractor (Phase A & B):  Shelly and Sands

      Construction Contractor (Phase C):  Double Z Construction