Sinclair Road Improvements - Morse Road to Strimple Avenue

DESCRIPTION AND BENEFITS:

This project scope consists of installing new sidewalk along both sides of Sinclair Road from Morse Road to Strimpe Avenue.

Uncurbed portions of Sinclair Road will be revised to improve stormwater conveyance. To accomplish the above goals; the project will impact, require improvements to, or require new facilities of the following for at least a portion of the project limits: pavement, curb, roadside grading, shoulders, ADA facilities, maintenance of traffic, traffic control, utilities and stormwater facilities, and temporary and permanent right‐of‐way acquisition. 

ESTIMATED SCHEDULE:

PHASESTARTFINISH
Design Spring 2020 Fall 2022
Right-of-Way Summer 2022 Summer 2023
Utility Relocations Summer 2023 Late 2023
Construction Late 2023* Late 2024*

*Subject to funding approval by City Council and weather conditions


ESTIMATED COSTS:

PHASECOST
Design $360,000.00
Right-of-Way $50,000.00
Construction $3.1 million


CONTACT INFORMATION:

City of Columbus Design Project Manager Kevin Thomas, P.E., (614) 645-6470
Designer Dynotec, Inc.
Construction contractor To be determined