Sinclair Road Improvements - Morse Road to Strimple Avenue
DESCRIPTION
AND BENEFITS:
This project scope consists of installing new
sidewalk along both sides of Sinclair Road from Morse Road to Strimple Avenue. Uncurbed portions of Sinclair Road will be
revised to improve stormwater conveyance. To accomplish the above goals; the
project will impact, require improvements to, or require new facilities of the
following for at least a portion of the project limits: pavement, curb,
roadside grading, shoulders, ADA facilities, maintenance of traffic, traffic
control, utilities and stormwater facilities, and temporary and permanent right‐of‐way acquisition.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Early 2020
|
Spring 2023
|
Right-of-Way |
Spring 2022
|
Fall 2023
|
Construction |
Spring 2024*
|
Fall 2024*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$300,000
|
Right-of-Way |
$50,000
|
Construction |
$3.1 million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Hannah Webber, P.E., (614) 645-2859
|
Designer |
Dynotec, Inc.
|
Construction
contractor |
To be determined
|