Warner Road Improvements between Hamilton Road and Harlem Road
This project will widen Warner Road between Breshly Way and
Harlem Road from 16 feet to 22 feet wide. Warner Road will be resurfaced
between Hamilton and Harlem roads. This project will include repair
work to the bridge crossing Rocky Fork Creek.
Schedule:Design: Spring 2016 – Fall 2016
Right-of-Way Acquisition: Begins winter of 2016
Construction: Spring 2018, subject to funding approval and weather conditions
Estimated Costs:Design: $85,000
Right-of-Way Acquisition: $60,000
Construction: $300,000
Contact Information:Project Manager: Benjamin
Farrell, P.E. (614) 645-2739Designer: Transystems
Construction Contractor: TBD