DESCRIPTION AND BENEFITS:

This is the first phase of a major widening project to construct new through and turn lanes of various configurations in the East Broad Street corridor from the east side of the I-270 interchange to the intersection of E. Broad Street and Reynoldsburg-New Albany Road. This first phase will construct new pavement for the widening and resurfacing of the existing pavement from the I-270 interchange to Outerbelt Street and will include traffic signal improvements; addition of a shared use path, sidewalk, street lighting, street trees, signal interconnect conduit; and incidental improvements such as drainage, traffic control, sediment and erosion control, water adjustments, and maintenance of traffic.

ESTIMATED SCHEDULE:

       
  PhASESTARTFINISH
  StudyFall 2017Spring 2020
  DesignSummer 2020Spring 2023
  Right-of-WaySummer 2022Late 2023
  Utility RelocationsSummer 2023Early 2024
  ConstructionEarly 2024*Late 2025*



 

*Subject to funding approval by City Council and weather conditions

 

ESTIMATED COSTS:

     
  PhASECOST
  Study$400,000
  Design$1.7 million
  Right-of-Way$2.2 million
  Utility Relocations$100,000
  Construction$16.0 million




CONTACT INFORMATION:  

     
  City of Columbus Design Project ManagerHannah Webber, P.E., (614) 645-2859
  DesignerTransystems Corporation
  Construction contractorTo be determined



VIRTUAL PUBLIC MEETING


A Virtual Public Meeting was held June 16, 2022 from 5:30-6:30 pm. A link to the WebEx Webinar recording can be found below

Click Here to view meeting recording 


The following documents were shared at the public meeting and can be accessed through the links below:

 


The public comment period will be open until Monday, July 18th, 2022. We have provided two ways to share comments: