DESCRIPTION AND BENEFITS:

This project scope consists of constructing sidewalks along the south side of Deshler Avenue from 18th Street to Lockbourne Avenue. Installation of the sidewalk will include curb ramps, drive approaches, curb, retaining walls, and may include stormwater drainage improvements in select areas. Project will install 3900LF of sidewalks.

ESTIMATED SCHEDULE:

PhASESTARTFINISH
Design Summer 2018 Spring 2021
Right-of-Way Summer 2020 Spring 2021
Construction Fall 2021* Summer 2022*

*Subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

PhASECOST
Design $240,000
Right-of-Way $120,000
Construction $1.1 million


CONTACT INFORMATION:

City of Columbus Area Engineer Tom Murphy, P.E., (614) 645-8455
Designer DLZ Ohio
Construction contractor G&G Concrete