This project scope consists of constructing sidewalks along the south side of Deshler Avenue from 18th Street to Lockbourne Avenue. Installation of the sidewalk will include curb ramps, drive approaches, curb, retaining walls, and may include stormwater drainage improvements in select areas. Project will install 3900LF of sidewalks.

ESTIMATED SCHEDULE:

Design: Summer 2018 – Summer 2020
Right-of-way acquisition: Fall 2019 – Fall 2020

Construction: Early 2021 – Summer 2021, subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

Design: $240,000 
Right-of-way acquisition: $117,000
Construction: $1.4 million

CONTACT INFORMATION:

City of Columbus design project manager: Hannah Webber, P.E., (614) 645-2859
Designer: DLZ Ohio
Construction contractor: To be determined