Design and Construction

Contact Information Department of Public Service
111 N. Front Street
Columbus, OH 43215
Office :  (614) 645-3111 
Fax :  (614) 645-7805 
Email : Contact Information

311
(614) 645-3111

Dublin-Granville Road at Ulry Road Intersection Improvements

DESCRIPTION AND BENEFITS:

The project will widen Dublin-Granville Road at the intersection with Ulry Road to provide an eastbound left turn lane and a westbound right turn lane. Dublin-Granville Road will also be widened and reconstructed between Ulry and Old Hamilton Road to accommodate a two-way left turn lane. Improvements will include the replacement of the existing strain pole traffic signal, sidewalk, a Shared-Use-Path (SUP), street trees, curb, storm sewer, and street lighting. Stormwater treatment will be required for the project. The SUP will be extended to approximately 100' west of Conifer Drive for a future tie-in to the Blendon Woods Metro Park.


ESTIMATED SCHEDULE:


PHASESTARTFINISH
Study Fall 2017 Late 2017
Design Late 2018 Early 2023
Right-of-Way Spring 2022 Spring 2023
Utility Relocations Spring 2022 Summer 2022
Construction Fall 2023* Summer 2024*

 

*Subject to funding approval by City Council and weather conditions


ESTIMATED COSTS:


PHASECOST
Study $50,000
Design $400,000
Right-of-Way $350,000
Construction $3.1 million

CONTACT INFORMATION:

 

City of Columbus Design Project Manager Hannah Webber, P.E., (614) 645-2859
Designer 2LMN
Construction contractor To be determined