Medina Ave - Roadway Improvement Project

DESCRIPTION AND BENEFITS:

This project will reconstruct Medina Ave from Hudson St to Briarwood Ave, which will serve as the main entrance to the new Linden Park recreation center.  Project improvements include the installation of new curb and gutter, sidewalk on the west side, storm sewer, street lighting, new ADA curb ramps at the intersections, and required post construction BMPs.   

 

ESTIMATED SCHEDULE:

Design: Early 2019 – Fall 2019

Right-of-way acquisition: Summer 2019 – Early 2020

Construction: Summer 2020 – Fall 2020, subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

Design: $250,000

Right-of-way acquisition: $75,000
Construction: $1.2 million

CONTACT INFORMATION:

City of Columbus Construction Area Engineer: Drew Griesdorn, P.E., (614) 645-6370
Designer: IBI Group

Construction Contractor: Columbus Asphalt Paving, Inc