FRA-161-12.83 (AT MAPLE CANYON) PID# 110376

DESCRIPTION AND BENEFITS:

 

This is the first phase of improvements planned for SR 161 from I-71 to Cleveland Ave corridor.  This limits of this phase are from Maple Canyon Ave to Cleveland Ave.  These improvements will include the addition of pedestrian and bike facilities, new traffic signals, pavement widening & resurfacing with raised medians with urban roundabouts on Maple Canyon Ave and Spring Run Dr/Parkville St. 

Additional information and exhibits about the project can be found on the Public Input site.

Comments for this project will be accepted until September 18, 2020.  Comments may be submitted to the project manager by mail or calling at the contact information below. 

ESTIMATED SCHEDULE:

 

Design: Spring 2019 – Summer 2021

 

Right-of-way acquisition: Late 2020 – Late 2021

 

Construction: Begins Spring 2022, subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

 

Design: $1.35 million
Right-of-way acquisition: $1.4 million

 

Construction: $9.5 million

CONTACT INFORMATION:

City of Columbus design project manager: Angela Fedak, P.E., (614) 645-3006

 

[email protected]

 

111 N Front. St.

 

Columbus, OH 43215

 


Designer: DLZ

 

Construction contractor: To be determined