Safe Routes to School / PID 109136
DESCRIPTION
AND BENEFITS:
This project will construct sidewalks along
the west side of Kingsford Road from Briggs Road to Eakin Road and along the
north side of Briggs Road from the existing sidewalk approximately 115' west of
Kingsford Road to Kingsford Road. Installation of the sidewalk will include
curb ramps and drive approaches.
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Fall 2019
|
Spring 2021
|
Right-of-Way |
Early 2021
|
Late 2021
|
Construction |
Spring 2022*
|
Fall 2022*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$150,000
|
Right-of-Way |
$30,000
|
Construction |
$400,000
|
CONTACT
INFORMATION:
City of Columbus Area
Engineer |
Tom Murphy, P.E., (614) 645-8455
|
Designer |
Korda Nemeth Engineering
|
Construction
contractor |
Strawser Paving
|