Norton Road Shared Use Path - Camp Chase Railroad to Hall Road
Project Scope:
This project will
construct a Shared-use path along the west side of Norton Road from The
intersection of Hall Road south to connect to the Camp Chase Trail.
Estimated Costs:
- Design: $227,821
- Right-of-Way
Acquisition: $30,000
- Construction: $655,000
Current Status: In
Design
Schedule:
- Design: Scheduled
to finish in spring 2020
- Right of way: Finish
acquisition summer 2020
- Construction:
Begin fall 2020
Contact Information:
- Design Project
Manager: Kevin Thomas tel (614) 645-6470
- Designer: Michael
Baker, Inc.
- Contractor: To Be
Determined