DESCRIPTION
AND BENEFITS:
This project consists of preliminary
engineering to examine potential alignments for an extension of Westbourne
Avenue from Taylor Station Road to Brice Road North/McCormick Boulevard and
detailed design for a first phase anticipated to be from Taylor Station Road to
Blossom Field Boulevard. This new corridor is intended to enhance the area
roadway network and add connectivity for all users.
ESTIMATED
SCHEDULE:
PhASE | START | FINISH |
Study |
Fall 2020
|
Early 2022
|
Design |
Late 2021
|
Early 2023
|
Right-of-Way |
Fall 2022
|
Early 2023
|
Utility
Relocations |
Early 2023
|
Spring 2023
|
Construction |
Spring 2023*
|
Late 2023*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PhASE | COST |
Study |
$250,000
|
Design |
$900,000
|
Right-of-Way |
$500,000
|
Construction |
$9.0 million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Hannah Webber, P.E., (614) 645-2859
|
Designer |
Gannett Fleming Engineers & Architects
|
Construction
contractor |
To be determined
|