This project consists of preliminary engineering to examine potential alignments for an extension of Westbourne Avenue from Taylor Station Road to Brice Road North/McCormick Boulevard and detailed design for a first phase anticipated to be from Taylor Station Road to Blossom Field Boulevard. This new corridor is intended to enhance the area roadway network and add connectivity for all users.

 

ESTIMATED SCHEDULE:

 

PhASESTARTFINISH
Study Fall 2020 Early 2022
Design Early 2022 Late 2022
Right-of-Way Summer 2022 Summer 2023
Utility Relocations Fall 2022 Spring 2023
Construction Spring 2023* Spring 2024*

 

*Subject to funding approval by City Council and weather conditions

 

ESTIMATED COSTS:

 

PhASECOST
Study $250,000
Design $800,000
Right-of-Way $500,000
Construction $6.0 million


CONTACT INFORMATION:

City of Columbus Design Project Manager Hannah Webber, P.E., (614) 645-2859
Designer Gannett Fleming Engineers & Architects
Construction contractor To be determined