DESCRIPTION AND BENEFITS:

This project consists of preliminary engineering to examine potential alignments for an extension of Westbourne Avenue from Taylor Station Road to Brice Road North/McCormick Boulevard and detailed design for a first phase anticipated to be from Taylor Station Road to Blossom Field Boulevard. This new corridor is intended to enhance the area roadway network and add connectivity for all users.

ESTIMATED SCHEDULE:

PhASESTARTFINISH
Study Fall 2020 Early 2022
Design Late 2021 Early 2023
Right-of-Way Fall 2022 Early 2023
Utility Relocations Early 2023 Spring 2023
Construction Spring 2023* Late 2023*

  *Subject to funding approval by City Council and weather conditions


ESTIMATED COSTS:

PhASECOST
Study $250,000
Design $900,000
Right-of-Way $500,000
Construction $9.0 million

CONTACT INFORMATION:

City of Columbus Design Project Manager Hannah Webber, P.E., (614) 645-2859
Designer Gannett Fleming Engineers & Architects
Construction contractor To be determined