High Street (South) at Dering Avenue Signal Replacement
Project Scope: This project scope consists of replacing the
existing traffic signal at the intersection of Dering Avenue at S. High Street.
Existing ADA compliant pedestrian facilities will be maintained and any
that are impacted or absent will be replaced or installed to full ADA compliance
as required.
Estimated Costs:
- Design: $120,000
- Right-of-Way
Acquisition: $30,000
- Construction: $450,000
Current
Status: In Design
Schedule:
- Design: Scheduled
to finish in summer 2022
- Right of way: Finish
acquisition spring 2023
- Construction:
Begin fall 2023
Contact Information:
- Design Project
Manager: Kevin Thomas tel (614) 645-6470
- Designer: GPD Inc.
- Contractor: To Be
Determined