Project Scope:
This project will install sidewalks along Grace Street between Orel Avenue and Eureka Avenue. The sidewalks will be located as follows: From Orel Ave to Warren Ave the sidewalk will be installed on the south side of Grace Street and from Warren Ave to Eureka Ave the sidewalk will be located along the north side of Grace Street.


Estimated Costs:

  • Design: $332,500
  • Right-of-Way Acquisition: $130,000
  • Construction: $2,700,000


Current Status: 


Schedule:

  • Design:  Scheduled to finish in Spring 2022
  • Right of way: Finish acquisition Spring 2023
  • Construction:  Begin Spring 2023


Contact Information:

  • Design Project Manager:  Kevin Thomas tel (614) 645-6470
  • Designer: Korda
  • Contractor: To Be determined