DESCRIPTION AND BENEFITS:

The project scope constructs sidewalks along Agler Rd from Sunbury Rd to Cassady Rd, along Sunbury Rd from Agler Rd north to Mifflin Middle School, and on Cassady Ave from Agler Rd north to Cassady Alternative Elementary School. This includes the installation of sidewalks, curb ramps, signing and pavement markings, and incidental improvements such as drainage, and maintenance of traffic

ESTIMATED SCHEDULE:

PHASESTARTFINISH
Design Early 2023 Early 2024
Right-of-Way Summer 2023 Summer 2024
Utility Relocations Summer 2023 Early 2025
Construction Spring 2025 Late 2025

*Subject to funding approval by City Council and weather conditions

ESTIMATED COSTS:

PHASECOST
Design $450,000
Construction $1,200,000
Right of Way $150,000

CONTACT INFORMATION:

City of Columbus Design Project Manager Andrew Frankhouser, P.E., (614) 645-3006
Designer Woolpert Engineering
Construction contractor To be determined