DESCRIPTION
AND BENEFITS:
The project scope constructs sidewalks along Agler Rd from
Sunbury Rd to Cassady Rd, along Sunbury Rd from Agler Rd north to Mifflin
Middle School, and on Cassady Ave from Agler Rd north to Cassady Alternative
Elementary School. This includes the installation of sidewalks, curb ramps,
signing and pavement markings, and incidental improvements such as drainage,
and maintenance of traffic
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Early 2023
|
Fall 2024
|
Right-of-Way |
Summer 2024
|
Summer 2025
|
Utility
Relocations |
Spring 2024
|
Late 2024
|
Construction |
Fall 2025*
|
Fall 2026*
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$500,000
|
Right-of-Way |
$150,000
|
Construction |
$1.2 Million
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Andrew Frankhouser, P.E., (614) 645-3006
|
Designer |
Woolpert Engineering
|
Construction
contractor |
To Be Determined
|