DESCRIPTION AND BENEFITS:

The project scope constructs sidewalks along Agler Rd from Sunbury Rd to Cassady Rd, along Sunbury Rd from Agler Rd north to Mifflin Middle School, and on Cassady Ave from Agler Rd north to Cassady Alternative Elementary School. This includes the installation of sidewalks, curb ramps, signing and pavement markings, and incidental improvements such as drainage, and maintenance of traffic

ESTIMATED SCHEDULE:

PHASESTARTFINISH
Design Early 2023 Fall 2024
Right-of-Way Summer 2024 Summer 2025
Utility Relocations Spring 2024 Late 2024
Construction Fall 2025* Fall 2026*

*Subject to funding approval by City Council and weather conditions


ESTIMATED COSTS:

PHASECOST
Design $500,000
Right-of-Way $150,000
Construction $1.2 Million


 

CONTACT INFORMATION:

City of Columbus Design Project Manager Andrew Frankhouser, P.E., (614) 645-3006
Designer Woolpert Engineering
Construction contractor To Be Determined