The project scope constructs
sidewalks along Agler Rd from Sunbury Rd to Cassady Rd, along Sunbury Rd from
Agler Rd north to Mifflin Middle School, and on Cassady Ave from Agler Rd north
to Cassady Alternative Elementary School. This includes the installation of
sidewalks, curb ramps, signing and pavement markings, and incidental
improvements such as drainage, and maintenance of traffic
ESTIMATED
SCHEDULE:
PHASE | START | FINISH |
Design |
Early 2023
|
Early 2024
|
Right-of-Way |
Summer 2023
|
Summer 2024
|
Utility
Relocations |
Summer 2023
|
Early 2025
|
Construction |
Spring 2025
|
Late 2025
|
*Subject to funding approval by City Council
and weather conditions
ESTIMATED
COSTS:
PHASE | COST |
Design |
$450,000
|
Construction |
$1,200,000
|
Right of
Way |
$150,000
|
CONTACT
INFORMATION:
City of Columbus
Design Project Manager |
Andrew Frankhouser, P.E., (614) 645-3006
|
Designer |
Woolpert Engineering
|
Construction
contractor |
To be determined
|