Intersection Improvements

DESCRIPTION AND BENEFITS:

This project consists of geometric and mobility improvements to the intersections of Greenlawn Avenue at S. Front Street and S. High Street at Greenlawn Avenue/Thurman Avenue. The road alignment will be improved so the intersection isn’t offset and motorists will be able to turn left onto High Street from Thurman Ave or Greenlawn Ave. This project will include traffic signal improvements, addition of a shared use path, sidewalk, and signal interconnect.  This project will also include incidental improvements such as drainage, traffic control, sediment and erosion control, waterline relocation, and maintenance of traffic.

ESTIMATED SCHEDULE:

PHASESTARTFINISH
Design Summer 2022 Summer 2024
Right-of-Way Summer 2023 Fall 2024
Utility Relocations Late 2023 Fall 2024
Construction Early 2025* Late 2025*

*Subject to funding approval by City Council and weather conditions

 

ESTIMATED COSTS:

PHASECOST
Design $500,000
Right-of-Way $500,000
Utility Relocations $200,000
Construction 2.8 Million


CONTACT INFORMATION:

City of Columbus Design Project Manager Elizabeth Buening, P.E, (614) 645-2410
Designer Crawford, Murphy, and Tilly
Construction contractor To be Determined

City of Columbus Design Project Manager Elizabeth Buening, P.E., (614) 645-2410
Designer Crawford, Murphy, and Tilly
Construction contractor To be determined