Front and Marconi Two Way Conversion
Description:
Project will convert Front Street from Broad Street to Hickory Street and Marconi Boulevard from Broad Street to Spring Street to two-way operation and upgrade the signals within the project limits to decorative downtown standard. Project also includes a new interconnect duct bank on Front Street and includes some new sidewalks, lighting and granite curb along Front and Marconi.
Costs:
Design: $420,095.21
ROW/Utilities: $0
Construction/Inspection: $6.5 million
Status:
Currently in design.
Schedule:
Design: December 2012 to Fall 2014
Construction: TBD
Contact Information:
Project Manager for design: Richard Ortman, P.E., tel. (614) 645-5465
Designer: Burgess and Niple LTD
Contractor: TBD